Selected Techniques: Phase 1: Wick Drain and Preload Program Phase 2: Controlled Modulus Columns (CMCs) Treatment Area: Surface area ~17,000m² Wick Drains ~ 2,000 1,550 Unit(s) CMCs Project Depth: up to 27.5mBGS This project involves the construction of a large recreational complex including 3 [...]
Warehouse: Vars, Ontario
jenniferlemarec2024-09-06T16:46:02+02:00Selected Technique: Controlled Modulus Columns Treatment Area: ~6,000m² Project Depth: 6m The development consisted of a multi-unit 1-storey warehouse approximately 6,630m2 with 10 loading docks in Vars, Ontario. The warehouse was designed for a 20 kPa slab load. Vars, Ontario [...]

Oceanfront Park development, Squamish, British Columbia
Menard Canada2024-07-31T22:48:15+02:00Selected Technique: Vibro Stone Coloumns & Dynamic Compaction Treatment Area & Maximum Depth (Vibro Stone Coloumns): 4,100 m² & 20m Treatment Area & Maximum Depth (Dynamic Compaction): 2,900 m² & 18m The Oceanfront Park development was planned to be constructed at the end of [...]
Fire Station: Contrecoeur, Quebec
Menard Canada2025-09-10T21:48:52+02:00Selected Technique: Controlled Modulus Columns (CMCs) Treatment Area: 2,500 m² Danis Construction mandated Menard Canada to provide ground improvement works for the future Contrecoeur fire station, including the soil for the foundations and the slab under the building. Ground Conditions A simplified stratigraphic profile was developed [...]
Extension d’usine: Plessisville, Quebec
Menard Canada2025-09-16T23:10:15+02:00Selected Technique: Dynamic Compaction Treatment Area: 11,106 m² Maximum Depth: 6 m Initially, Menard Canada started ground improvement works for the factory in 2015. Dynamic Compaction was used to increase the bearing capacity of the foundations during the construction of the buildings. The next [...]
Airport Building: Boul. Bagotville, Quebec
Menard Canada2025-09-10T21:07:11+02:00Selected Technique: Vibro Compaction + Dynamic Compaction + Dynamic Replacement Treatment Area: 1,6944m Maximum Depth: Dynamic Compaction 10m Vibrocompaction 20m Dynamic Replacement 20m Service from Menard Canada was requested by Sullivan & Son to improve the ground under the future Canadian Armed Forces building [...]

Student Residence, Mc Master University: Hamilton, Ontario
Menard Canada2025-06-20T17:23:44+02:00Selected Technique: Controlled Modulus Columns (CMCs) Elements Installed: 753 Unit(s) CMCs The McMaster Main Street Undergraduate Residence project involved the construction of an up to 15-storey plus mechanical penthouse residential structure located at 1190 Main Street West, Hamilton, Ontario. The undergraduate residence, named after the [...]

Birchley Park, Residential Housing – Toronto, Ontario
menardcanadainc2024-07-22T20:44:36+02:00Selected Technique: Rapid Impact Compaction Treatment Area: 12,000 m² Treatment Depth: 6 m Menard Canada was selected by Diamond Kilmer Developments to provide the required resources and quality control associated with the ground improvement work of Rapid Impact Compaction (RIC) for the proposed Street [...]
Metro Warehouse: Terrebonne, Québec
menardcanadainc2024-07-22T20:11:13+02:00Selected Techniques: Controlled Modulus Columns (CMC) Dynamic Compaction Treatment Area: 60000 m² Menard Canada was commissioned by Metro Inc to improve the soil under the future food distribution warehouse located at the southeast corner of the intersection of boulevard de la Pinière Ouest and 20th [...]
Multi-Housing: Saint-Charles-Borromée, Québec
Menard Canada2023-11-16T16:23:02+01:00Selected Technique: Dynamic Compaction Treatment Area: 1,866 m² Groupe Evex approached Menard Canada to improve the soil of the foundations and the slab under the multi-unit building at 678 rue de la Visitation in Saint-Charles-Borromée, Quebec. The area of the land to be improved was [...]