A Rapid and Cost-Efficient Approach to Ground Improvement

Controlled Modulus Columns (CMC)® are concrete columns placed in a grid network that effectively spreads the applied high loads from the structure above and between the ground and the grid of CMCs. CMCs are often mistaken for other deep foundation solutions, such as conventional auger-cast-piles or drilled caissons. Those piling systems are designed as structural elements, unlike CMC’s unique installation that results in stiffened soils capable of supporting shallow footings and slab-on-grade.

  • Zero-spoils: No excess soils to remove
  • Minimizes differential settlement
  • Vibration-free displacement process
  • Soft soils 
  • Organic clays 
  • Loose sands 
  • Treat soils up to 50m deep 
  • 280-500mm-diameter elements installed 

CMCs are installed by advancing the displacement tooling to the target depth and filling with cement-based grout as the tooling is retracted – grout is discharged at the base of the hollow tooling under controlled, and limited pressure to ensure the continuity of the grouting process. CMCs have been installed to depths of over 45 m. 

How it Works

CMCs work by utilizing reverse flight augers to effectively displace the soil laterally, significantly densifying the soil around the CMC, which in turn improves the load transfer to the installed element; essentially, they draw in the load from above and transmit those forces downward into more competent soils below. The combined effect of reinforcement and densification from the installation process improves the characteristics of the ground resulting in a composite system. The load from the structure is then distributed to the soil and CMCs, with the proportion of load carried by the soils. Depending on the stiffness of the soil – the stiffer the soil, the higher proportion of the stresses will be carried by the soil. Typically, a layer of compacted stone known as a Load Transfer Platform (LTP) is designed to span across the top of the CMCs to help distribute the load from the structure to the elements.


Our Promise of Quality Assurance

Menard Canada’s ground improvement proposals always come with straightforward pricing, so you will never have to worry about any unexpected project extras. The cost that we quote you is your project’s cost; it’s that simple. Furthermore, we will always work to meet and exceed all your project expectations by performing tasks using the most thorough quality control measures possible to ensure a positive project outcome for your project; this is our promise to you.

We invite you to review our testimonials below and see what makes Menard Canada different.

“It was a pleasure to work with the Menard Canada team. Our high-rise development was challenged by unsuitable fill, high groundwater conditions, and adjacent historic structures. The installation of Menard’s ground improvement solution was executed within the allotted budget, schedule, and without any impact to the adjacent structures.”

Nicholas Schady, Superintendent, SKYGRiD Construction Inc.

“We have worked with Menard to provide a Design- Build proposal for many projects that shared the trait of having poor soil conditions. Menard provided professional assistance and managed the soil improvements without issue. The cost savings, time savings, and ease of construction were all realized. We would strongly recommend them for all our future projects.”

Raymond Van Groll, M.Sc. (Eng)| P.Eng. | Managing Partner, ATKINS + VAN GROLL

“Their expertise offered us complete solutions, including engineering and construction. From a simple geotechnical study, they can validate possible and alternative methods in a very short time. Being very available and creative, they have become a reference for our projects that require a more advanced geotechnical expertise.”

Karine Bourque, General Manager, Ronam Constructions Inc.

“Menard was well prepared for the job, showed up with all of the equipment that was needed and started right away. There were some challenges, and extra equipment was required, but Menard got it to the site quickly. The Menard team was good at reporting progress and challenges.”

Richard Gagné, P.Eng., Project Manager, Pembina Pipeline Corporation

“Generally quite impressed with the work Menard did. The process itself is simple and effective. The project setup, coordination and installation were straightforward. The field staff were easy to work with and were accommodating with other enabling site works.”

Radu Grumeza, P.Eng | LEED Green Associate | Assistant Construction Manager, CANA Group of Companies

“It’s been an absolute pleasure working with Menard. From the first day you arrived, we noticed the professionalism and preparation that was put in to execute this job well. You’ve allowed us to get one month ahead of schedule by starting two weeks early and finishing two weeks early.”

Zain Jessani, P.Eng. | Project Engineer, Aecon Construction and Materials Limited (ACML)

“Menard did an excellent job installing the stone columns for us in extremely challenging ground conditions; it was much appreciated!”

Richard Gagné, P.Eng., Project Manager, Pembina Pipeline Corporation

“The Controlled Modulus Column method avoided the impacts of deep shoring and dewatering while limiting the volume of excess soil generated on our site. All of this combined to simplify our foundation construction and get our project out of the ground.”

Nicholas Schady, Superintendent, SKYGRiD Construction Inc.

“Menard turned up on site as expected and worked without interruption to complete their scope. We are very pleased with Menard’s performance, and they will be our first contact for future projects requiring soil improvement.”

John Gregory, P.Eng | Construction Manager, Ark Construction LTD.

“As a general contractor, we often have to find efficient and economical solutions when soil quality is an issue in a project. On many occasions, Menard’s soil improvement solutions have significantly reduced the cost of a project. Whether it is through dynamic compaction or Vibro replacement, we have often been able to avoid pile foundations, thus reducing the budget and the schedule. In addition, Menard’s soil improvement solutions allow our clients greater flexibility in the future modifications they wish to make to their building.”

Karine Bourque, General Manager, Ronam Constructions Inc.

“The Menard team went out of their way to make the process both pleasant and efficient and wouldn’t have any reservations about using Menard in the future.”

Nicholas Schady, Superintendent, SKYGRiD Construction Inc.

“We contracted Menard Canada for the ground improvement works under two residential buildings and an amenity building in Chatham, Ontario. Their team worked with the Structural and Geotechnical Consultants during the design phase to find a solution to the local ground conditions – which proved to be very beneficial for the development of this site and the project as a whole. They then carried out the designed ground improvements on site; our team appreciated Menard Canada’s professionalism and proactivity. After the completion of the work, the Menard Canada team was available for questions and always provided feedback right away. Menard Canada would definitely be our first choice for any ground improvement on our next projects.”

William Layng, Jr. Project Manager, RHC